Implementation Recovery

Background

Company with over $3 billion in revenue continued to have failed software implementation of regulatory supported application. Multiple attempts had failed implementation over a six year period.

The Needs

Regulatory requirements and overview was increasing, penalties were increasing, and manual processes were becoming burdensome. Software add-ons were needed and requested to be completed promptly.

The Results

Within 6 months, the project was completed and tested. The company immediately processed millions of records, saving an estimated $2 million over three years. The new system ensured compliance with state and federal regulations.

  • Project completed and tested within six months.
  • Company was immediately able to run millions of records through the system.
  • An estimated $2 million was saved over a three year period.
  • The company was compliant with state and federal regulatory requirements.

Services Rendered

  • Partnership
  • Sponsorship
  • Communication Clarity
  • Project Management
  • Software Implementation
  • Regulatory

More Case Studies

A software company was running international and domestic development teams to support their primary products…
Company with over $3 billion in revenue continued to have failed software implementation of regulatory supported application…
An enterprise covered multiple locations across three states. Historical information identified that the organization was losing millions…